SUP13-08 (Denbury Pipeline)
An SUP request for a proposed CO2 pipeline to be located within an existing Centerpointe power corridor easement for approximately 24,000 feet, generally located north and south of FM 518, west of Landing Boulevard, and east of Westover Park Avenue in League City, Texas.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: February 25, 2014
- P&Z Commission: February 3, 2014
- Current Status: Approved by City Council on February 25, 2014 as Ordinance Number 2014-06 (PDF).
- Project Manager: Email the Planning Department.
Z13-08 (CCISD)
A rezoning request to rezone approximately 24.4 acres of property from "CM" (Commercial Mixed-Use) to "PS" (Public and Semi-Public), generally located east of West NASA Road and south of FM 528, northeast of Clear Creek Independent School District Agricultural Center.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: January 28, 2014 and April 22, 2014
- P&Z Commission: January 6, 2014
- Current Status: Request was approved Council on April 22, 2014 as Ordinance Number 2014-15 (PDF).
- Project Manager: Email the Planning Department.
SUP13-07 (AT&T Mobility)
An SUP request for a cell tower on 2.1 acres of land, generally located on the southeast corner of I-45 and Wesley Drive with the address of 352 North Gulf Freeway.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: Changed from January 14, 2014 to March 11, 2014
- P&Z Commission: January 6, 2014 and February 3, 2014
- Current Status: Approved by City Council on March 25, 2014 as Ordinance Number 2014-08 (PDF).
- Project Manager: Email the Planning Department.
Z13-06 (352 North Gulf Freeway)
A rezoning request to rezone 2.1 acres from "CN" (Neighborhood Commercial) to "CM" (Mixed-use Commercial), generally located on the southeast corner of I-45 and Wesley Drive with the address of 352 North Gulf Freeway.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: January 14, 2014
- P&Z Commission: December 16, 2013
- Current Status: Approved by City Council on January 28, 2014 as Ordinance Number 2014-01 (PDF).
- Project Manager: Email the Planning Department.
SUP13-05 (BridgeTex Pipeline)
An SUP request to install a pipeline along an existing 100-foot wide Centerpoint Energy / Interurban Right-of-Way easement being approximately 16,310 feet in length located north and south of FM 518, League City Parkway, and FM 646, west of Highway 3.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: Changed from January 14, 2013 to February 11, 2014
- P&Z Commission: January 6, 2014
- Current Status: Approved by City Council on February 25, 2014 as Ordinance Number 2014-03 (PDF).
- Project Manager: Email Planning Department.
Z13-05 (Westwood Subdivision)
A zoning request for five tracts of land within the Westwood Subdivision, located south of FM 518, east of the western city limits and west of Maple Leaf Drive.
- Map and Notification (PDF) (Updated)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: Changed from November 19, 2013 to December 17, 2013
- P&Z Commission: Changed from November 4, 2013 to December 2, 2013
- Current Status: Approved by City Council on December 17, 2013 as Ordinance Number 2013-52 (PDF).
- Project Manager: Email the Planning Department.
SUP13-06 (AT&T Mobility)
An SUP request for a cell tower on the Big League Dreams property, located on the north of Big League Dreams Parkway and west of Interstate 45 with the approximate address being 1150 Big League Dreams Parkway.
- Map and Notification (PDF) (Updated)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: Changed from December 3, 2013 to December 17, 2013
- P&Z Commission: Changed from November 4, 2013 to December 2, 2013
- Current Status: Approved by City Council on December 17, 2013 as Ordinance Number 2013-53 (PDF).
- Project Manager: Email the Planning Department.
SUP13-03 (Driver's Auto)
An SUP request for a mechanics shop on a property located on the north side of FM 518, east of Bay Area Boulevard and west of Oak Creek Drive with the approximate address being in the 4800 block of FM 518.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: October 8, 2013
- P&Z Commission: September 16, 2013
- Current Status: Approved by City Council on October 22, 2013 as Ordinance Number 2013-43 (PDF).
- Project Manager: Email the Planning Department.
SUP13-04 (Stripes Convenience Store)
An SUP request for a gas station with a convenience store on a property located on the northwest corner of FM 518 and Wesley Drive with the approximate address being 1520 FM 518.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: September 10, 2013
- P&Z Commission: August 19, 2013
- Current Status: Request was denied by City Council
- Project Manager: Email the Planning Department.
Z13-03 (FM 646 Commercial)
A zoning request to rezone 24.89 acres from "RSF-7" (Single-family residential with a minimum lot size of 7,000 square feet) to "CG" (General Commercial) for property located south of FM 646 and the the entrance to Whispering Lakes Ranch and approximately 2,700 feet to the east of South Shore Boulevard.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: June 25, 2013
- P&Z Commission: June 3, 2013
- Current Status: Approved by City Council on July 9, 2013 as Ordinance Number 2013-30 (PDF).
- Project Manager: Email the Planning Department
Z13-02 (Historic District Overlay)
A zoning request to add a Historic District Conservation Overlay to existing properties within the Historic District being approximately 181.6 acres located north of Lewis Street, west of Wisconsin Avenue, east of Perkins Avenue and south of Clear Creek, excluding properties on 7th Street and the Township Subdivision.
- Map and Notification (PDF) (Updated)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: May 28, 2013 (Re-scheduled to June 11, 2013)
- P&Z Commission: May 6, 2013
- Current Status: Approved by City Council on June 25, 2013 as Ordinance Number 2013-24 (PDF).
- Project Manager: (Email the Planning Department)
SUP13-02 (Mike & Jr. Food Mart)
An SUP request for a gas station with a convenience store on a property located on the southeast corner of FM 528 and West NASA Boulevard with the approximate address being 1595 FM 528.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: May 28, 2013
- P&Z Commission: May 6, 2013
- Current Status: Approved by City Council on June 11, 2013 as Ordinance Number 2013-19 (PDF)
- Project Manager: Email the Planning Department.
SUP13-01 (Stripes Convenience Store)
An SUP request for a gas station with a convenience store on a property located on the northwest corner of FM 518 and Wesley Drive with the approximate address being 1520 FM 518.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: March 12, 2013 (Withdrawn)
- P&Z Commission: February 18, 2013
- Current Status: Withdrawn by Applicant on March 1, 2013
- Project Manager: Email the Planning Department.
Z13-01 (Brittany Business Park)
A request to rezone approximately 21.22 acres from "CM" (Commercial Mixed Use) to "CG" (General Commercial) for properties located west of Interstate 45 and east of Hobbs Road with the approximate addresses being 1101 to 1231 Butler Road.
- Map and Notification (PDF)
- Staff Report (PDF)
- Public Hearing Dates:
- City Council: February 26, 2013
- P&Z Commission: February 4, 2013
- Current Status: Approved by City Council on March 12, 2013 as Ordinance Number 2013-11 (PDF).