Streets - Roadway Development CIP Projects

The Streets program totals $18.4 million over the five year period with 37 percent from Galveston County and Grant funds, 48 percent funded from prior bond proceeds or dedicated funds, and 15 percent from future bond sales.  The FY 2015 projects total $16.4 million including $7.9 million for environmental approval, right-of-way purchase, and construction of the Five Corners Realignment project, $7.4 million for the right-of-way and construction of Calder Rd (Ervin to League City Parkway), $300K for sidewalk repairs and a segment of new sidewalks along Davis Rd, $208K for resurfacing the second half of Texas Ave (Webster St to FM518), $320K for land purchase for future improvements to the Butler/Turner corridor, and $150K for repair to targeted sections of Landing Blvd.    

Also included in the five-year plan are the design for improvements to the Butler/Turner corridor, and the design of Wesley Drive reconstruction.


View larger map

Projects In Progress At A Glance: (as of February 2017)

Calder Rd - Ervin to LC Pkwy:  Land acquisition continues; anticipate utility relocation February/March 2017 pending land acquisition.  Construction contract awarded September 13, 2016 with NTP issued for February 2017.

Five Corners Realignment: Council awarded design with Klotz April 22, 2014;  TxDOT Environmental approval received October 2015. ROW agent to assist with land acquisition beginning November 2015;  TxDOT construction bid January 2017; anticipated construction to begin April 2017.  Utility relocations began September 2016; anticipated utility relocations complete February 2017.

N Landing Blvd Extension: City’s consultant (Parsons-Brinkerhoff) and City staff to meet with TxDOT in January 2017 to discuss Preliminary Engineering Report (August 2016) and TxDOT recommended alignment adjustment (south of Clear Creek).  City’s consultant and City staff to meet with Houston Galveston Area Council (HGAC) late February/early March 2017 to discuss requirements for re-submittal to HGAC for construction budget increase from $18.5 million to $39.4 million.  First TxDOT public meeting for environmental comments scheduled for March 7, 2017 at Johnnie Arolfo Civic Center, League City.

Roadway Impact Fee StudyCouncil awarded development of a roadway impact fee study by Freese and Nichols August 27, 2013;  completion of study delayed while P&Z works through project recommendations; anticipate completing study Summer 2017.

Butler/Turner Improvements: 
Land acquisitions complete.  Project will be funded under Reinvestment in the future.

Hobbs/FM 518 Signal Improvements (TxDOT): FY 2016 project: This signal replacement is included in the TxDOT project for I-45 from Nasa 1 to .45 miles south of FM 518.

Master Mobility Plan:  Design awarded to Freese and Nichols, Inc. on August , 2016.  Project still in early stages, F&N preparing to send initial plan to HGAC to run with their model.  Project is at 5-10% completion.


Need More:
Looking for financial information or more? You can view the most recent quarterly and monthly status reports with more detail by clicking on the following: Status Reports Quarterly reports will give you where we are at in the budget for the project and monthly reports will give you the latest status updates on active project.