Brittany Bay Subdivision Drainage Improvements

Budget: $500,000

Scope of work: Increase capacity and efficiency of existing drainage easements to improve flow. Improve easements/rights-of-way with either earthen swales or concrete channels for unrestricted flow paths to Landing Ditch.

Subdivisions, areas, or streets impacted: Brittany Bay

Brittany Bay Subdivision Drainage Improvements aerial map

Brittany Bay Subdivision Drainage Improvements timeline schedule

Project Status as of March 2021

GO Bond Project; notified July 24th CDBG-DR will pay 75% of project cost with City portion at 25%; grant kickoff meeting with GLO Sept 16th; RFQ selection process for grant guidelines followed to select design engineer; proposal requested from RPS Engineering in late-March 2021; first draft received April 7th; anticipate design award in May 2021.   

Original Schedule    

The original schedule, as of September 2019, shows design in progress from quarter 1 of 2020 through quarter 2 of 2021 for Brittany Bay Subdivision Drainage Improvements. Land acquisition is programmed from quarter 3 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of March 2021, for the Brittany Bay Subdivision Drainage Improvements project shows the grant application completed from quarter 1 of 2019 through quarter 3 of 2020. Grant award complete in quarter 4 of 2020 with grant kick-off in progress in quarter 1 of 2021. RFQ for design services as required by grant is programmed in quarter 2 of 2021. Design is programmed from quarter 3 of 2021 thru quarter 3 of 2023. Land acquisition is scheduled to be from quarter 4 of 2022 through quarter 3 of 2023. Construction bidding is programmed for quarters 3 & 4 of 2023. Construction is programmed for quarter 4 of 2023 through quarter 4 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.