Countryside Subdivision Drainage Improvements

Budget: $350,000

Scope of work: Enhance capacity and efficiency of existing drainage easements to improve flow and maintenance. Improve easements with either earthen swales or concrete channels for unrestricted flow paths to Magnolia Creek.

Subdivisions, areas, or streets impacted: Countryside

Countryside Subdivision Drainage Improvements aerial map

Countryside Subdivision Drainage Improvements timeline schedule

Project Status as of June 2021

GO Bond project; design agreement approved by Council November 5, 2019; 90% plans were reviewed by the City and City comments were addressed in May 2021; plans have been revised to alleviate constructability issues; land acquisition began October 2020; anticipate construction in the summer of 2021 pending homeowner removal of conflicts within easements.

Original Schedule

As of September 2019, it shows design in progress in quarter 1 of 2020 through quarter 2 of 2021 for Countryside Subdivision Drainage Improvements. Land acquisition is programmed from quarter 3 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of June 2021, for the Countryside Subdivision Drainage Improvements project shows design in progress from quarter 4 of 2019 through quarter 2 of 2021.  Land acquisition is shown in progress from quarter 4 of 2020 through quarter 3 of 2021. Construction bidding is programmed for quarter 3 of 2021. Construction is programmed for quarter 4 of 2021 through quarter 4 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.