Dove Meadows Detention Pond

Budget: $5.8 million

Scope of work: Purchase land and construct a 115 acre-foot detention pond east of Blue Wing Drive and west of Borden’s Gully.

Subdivisions, areas, or streets impacted: Dove Meadows

map

project timeline-dove meadows-01

Project Status as of March 2021

Project from GO Bond Election, design awarded 5/28/19; wetlands were discovered and after additional information was acquired, City staff worked with Design Engineer to vet options; received updated design drawings with small change in scope to minimize land needed; second 90% design plans were submitted for City review Feb 10, 2021; City comments returned to engineer on March 3; Nationwide USACOE permit type required with a 9-12 month timeline from application in November 2020; City’s legal department working to obtain land which may require eminent domain; 90% construction plan comment review meeting held with Engineer week of April 5th. Acquisition will be done by imminent domain which will take 3-6 months. Need Right-of-Entry to perform tree survey on the parcel; legal is working to obtain. 100% design plans will be finalized after environmental clearance is obtained; project may start construction as early as the end of 2021 pending permitting requirements. Construction length TBD as construction will be bid and awarded based on time and cost.

Original Schedule

As of September 2019, shows design in progress in quarter 2 of 2019 through quarter 3 of 2020 for Dove Meadows & Borden's Gully Detention Pond. Land acquisition is programmed from quarter 1 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 1 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

As of March 2021, for the Dove Meadows & Borden's Gully Detention Pond project shows design complete from quarter 2 of 2019 thru quarter 1 of 2021. Final design is programmed for quarter 4 of 2021. Land acquisition is shown in progress from quarter 1 of 2020 through quarter 3 of 2021. Permitting is shown in progress from quarter 4 of 2020 through quarter 3 of 2021. Construction bidding is in programmed for quarters 1 & 2 of 2022. Construction is programmed for quarter 3 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.