Newport and Ellis Landing Subdivision Drainage Improvements

Budget: $800,000

Scope of work: Increase capacity and efficiency of existing drainage easements to improve flow. Improve easements/rights-of-way with either earthen swales or concrete channels for unrestricted flow paths to Newport Ditch.

Subdivisions, areas, or streets impacted: Newport and Ellis Landing

map

project timeline-newport and ellis landing drainage-01

Project Status as of March 2021

GO Bond Project; project awarded CDBG-DR funding; grant is awarded; RFQ selection process for grant guidelines followed to select design engineer; proposal requested from RPS Engineering in late-March 2021; first draft received April 7th; anticipate design award in May 2021.

Original Schedule

The original schedule, as of September 2019, shows design in progress from quarter 1 of 2020 through quarter 2 of 2021 for Newport & Ellis Landing Drainage Improvements. Land acquisition phase begins in quarter 3 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of March 2021, for the Newport & Ellis Landing Drainage Improvements project shows grant application complete in quarter 1 of 2019 through quarter 3 of 2020. Grant award was complete in quarter 4 of 2020 with grant kickoff in progress in quarter 1 of 2021. RFQ for design services required by grant is programmed for quarter 2 of 2021. Design is scheduled from quarter 3 of 2021 through quarter 3 of 2023. Land acquisition is programmed from quarter 4 of 2022 through quarter 3 of 2023. Construction bidding is in programmed for quarter 3 of 2023 through quarter 4 of 2023. Construction is programmed for quarter 4 of 2023 through quarter 4 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.