Oaks of Clear Creek Overland Flow and Acquisition

Budget: $1.3 million

Scope of work: Purchase land and construct a detention pond to enhance subdivision drainage directly into Bradshaw Ditch.

Subdivisions, areas, or streets impacted: Oaks of Clear Creek

drainage

project timeline-oaks of clear creek overland flow-01

Project Status as of March 2021

Project from GO Bond Election, advertised for construction bid March 23rd with bid opening scheduled for April 21st; presentation to Council for award May 11th meeting. Home at 1340 Deer Ridge has been demolished. *Construction delayed from original schedule based on closing on property needed for improvements; construction time will be established as part of award of bid as contractor bids on cost and time as part of contract award.

Original Schedule

The original schedule, as of September 2019, shows design in progress from quarter 2 of 2019 through quarter 3 of 2020 for Oaks of Clear Creek Overland Flow & Acquisition. Land acquisition phase begins in quarter 1 of 2020 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 1 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of March 2021, shows design complete in quarter 2 of 2019 through quarter 4 of 2020 for the Oaks of Clear Creek Overland Flow & Acquisition project. Land acquisition was completed in quarter 2 of 2020 through quarter 4 of 2020. Demolition of the home property completed in quarter 1 of 2021. Construction bidding is in progress for quarter 1 & 2 of 2021. Construction is programmed for quarter 3 of 2021 through quarter 3 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.