Rustic Oaks Subdivision Drainage Improvements

Budget: $400,000

Scope of work: Enhance capacity and efficiency of existing drainage easements to improve flow. Improve easements/rights-of-way with either earthen swales or concrete channels for unrestricted flow paths to Magnolia Creek and Cedar Gully.

Subdivisions, areas, or streets impacted: Rustic Oaks

Rustic Oaks Subdivision Drainage Improvements aerial map

Rustic Oaks Subdivision Drainage Improvements timeline schedule

Project Status as of March 2021

GO Bond project; design agreement approved by Council November 5, 2019; after receiving direction on scope from City staff, the design consultant is preparing 90% plans currently with anticipation of plan submittal for review in April 2021; land acquisition began October 2020; anticipate construction summer 2021.

Original Schedule

The original schedule, as of September 2019, shows design beginning in quarter 1 of 2020 through quarter 2 of 2021 for Rustic Oaks Subdivision Drainage Improvements.  Land acquisition phase begins in quarter 3 of 2020 through quarter 2 of 2021.  Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2022.  Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of March 2021, shows design of Rustic Oaks Subdivision Drainage Improvements in progress from quarter 4 of 2019 through quarter 2 of 2021.  Land acquisition begins in quarter 4 in 2020 through quarter 3 of 2021.  Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.