The Landing Subdivision Drainage Improvements

Budget: $500,000

Scope of work: Increase capacity and efficiency of existing drainage easements to enhance flow. Improve easements/rights-of-way with either earthen swales or concrete channels for unrestricted flow paths to Landing Ditch.

Subdivisions, areas, or streets impacted: The Landing

map

Landing drainage project timeline

Project Status as of March 2021

GO Bond Project; project awarded CDBG-DR funding; grant is awarded; RFQ selection process for grant guidelines followed to select design engineer; proposal requested from RPS Engineering in late-March 2021; first draft received April 7th; anticipate design award in May 2021.

Original Schedule

The original schedule, as of September 2019, shows the preliminary study phase underway in 2019 with completion in quarter 4 of 2019 for The Landing Drainage Improvements. Design and land acquisition phases begins in quarter 1 of 2020 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 2 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of March 2021, shows the completion of a grant application in quarter 3 of 2020 for The Landing Drainage Improvements. Grant award and kickoff were quarter 4 of 2020 and continue in quarter 1 of 2021. RFQ for design services per the grant requirements are programmed for quarter 2 of 2021. Design begins quarter 3 of 2021 and continues through quarter 3 of 2023. Land acquisition begins in quarter 4 in 2022 through quarter 3 of 2023. Construction bidding is scheduled for quarter 3 and 4 of 2023 with construction following through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.